Master Engineering Technology

RAM Assessment Tool

Reliability, availability & maintainability for process plant equipment. Enter the equipment list, take failure data from the OREDA-style library or your own, and get analytic RBD results plus Monte Carlo production availability.

Quick start: equipment list
  1. Pick an example under Study / facility, or choose Custom study and press Add equipment.
  2. Set the study basis: logistic delay, PM treatment, crews, common-cause β and turnaround.
  3. Add one row per block of identical units: units installed and capacity per unit set the redundancy (3 × 50 % reads 2oo3).
  4. Keep Data = Library to use the failure data library, or switch a row to User to type its own λ, MTTR and PM.
  5. For identical parallel trains, add a train group and set the Train column of the per-train items. For a combined cycle, add a combined-cycle group and mark each row as GT side, HRSG or steam cycle.
  6. Add external and operational events (grid, weather, supply, offtake, trips, upsets) and set the restart and off-spec time in the study basis.

Study basis

These settings apply across every tab. Downtime per corrective event = MTTR + logistic delay (mobilisation, spares, permits).

Repairs and common cause
Fewer crews than units makes repairs queue
Applied to blocks of 2+ units unless the row sets its own
Turnarounds, trips and restarts
0 = no plant turnaround
If unspared PM is done in the turnaround, set PM to Ignore
Added after every full stop once its cause is cleared
Running but not sellable; counted as lost
Power generation (N−1 and spinning reserve)
Hot day, fuel gas and altitude, against nameplate
Indicative; use OEM data (ISO 8528-5 for engines)
Share of set trips that black out the plant despite the spare
Re-energise and resynchronise; then the plant restart applies
Parallel operation (blocks of 2+ units)
Tick rows in the Parallel penalty column
Flow bias and unequal curves; not applied to substation equipment
Isolation and check valves, recycle, seals, flanges
Congested layout and access, ×MTTR

Parallel trains

Use a train group when identical process trains run side by side, such as 2 × 50 % LNG trains. Assign equipment to the group in the Train column and enter it per train (e.g. one MR compressor, 1 × 100 % of its train). Each train runs at the rate of its weakest item; the group delivers the sum of its trains. A train turnaround takes one train down at a time, staggered across the group. A combined cycle group links N gas turbine trains to one steam cycle: set each row as GT side, HRSG or steam cycle in the Train column.

Group nameTypeTrains / GTsCapacity / train %Items per trainTrain TA every (yr)Train TA daysGT share %Open-cycle bypassConfigurationTrain full-rate AGroup PA

No train groups. All equipment is plant-wide.

External and operational events

Losses not caused by an equipment failure: grid disturbances, weather, feed or offtake interruptions, spurious trips, process upsets. Each event stops the plant, or cuts it to the rate you set, for its duration. Storage cover is the hours of tankage that absorb a supply or offtake interruption before production stops.

OnEventCategoryEvents / yrOnce every (yr)Mean duration (h)Rate during (%)Storage cover (h)Restart afterLost / yr

No events. Only equipment failures, PM and turnarounds are counted.

Equipment list

One row per block of identical units. Installed count and capacity per unit set the redundancy, e.g. 3 × 50 % is 2-out-of-3. Plant-wide rows marked In RBD are in series for production. Spare mode Standby means spare units sit idle and must start on demand.

In RBDTag(s)ServiceSystemTrainEquipment classData UnitsCap / unit %Spare modeFail to startCCF β %Parallel penaltyTrip cascade %Rate if lost %λ crit /10⁶ hMTTR hPM h/yr/unit ConfigurationUnit ABlock PA